Sunday, May 16, 2010

Reflection Page

What project to do?

Sok Ying had proposed to the team to make "ERP Implementation" to be our project as she and myself  had gone through the Oracle 11i Implemenation in our previous company. This was to replace the standalone legacy systems that had been used by different functions or departments. Thus, data analysis was a very tedious task as we need to extract and compile data/information from different system.
The project was a big one as the duration of the project took about 1 year to implement. Further enhancement was done after its implementation.

We were from the planning department. As such, we were involved in the implementation of the Oracle 11i ASCP, ie Advanced Supply Chain Planning tool.  There were a lot of activities involved in the implementation.

Some examples of the tasks are as follows:
  • For Data migration. Have to input information eg product family, product, resource, cycle time, into a spreadsheet. The data will then be downloaded by the IT guys who wrote the script for the data migration. Planners will then need to review and correct on any fallouts ie any data that failed to migrate over due to wrong setting and so others.
  • Doing mock testing,
  • Adoption and learning of the new system,
Steven
9May


Thoughts
If we will to work on a full ERP implementation, it may take about 1 year or more to complete. Thus, the team will propose to the sponsor that we will target to complete the "Planning and Procurement" module first.


Steven
23May


Review and correct
The team have reviewed through the feedback list from Janet. We have made some changes and correction but we are not so sure on some of them.

Need to review with Janet on 3Jun to clear our doubts and also to confirm whether what we have corrected is per her requirement in the feedback list.

Steven
30May


Actions
We have reviewed and made changes to the responsiblity matrix afer a brief discussion with Janet last week. We will focus 100% on planning and procurement and completed the matrix.

We wanted to continue to apply the WBS concept to costing. However,we think that is better to send the updated matrix for Janet to review first. Hopefully, there is no more changes to updated matrix and we will proceed to do the costing on a week day to complete for submission on 17th June. Even if there is changes to the matrix, we can still proceed and make changes along the way.

Sok Ying
14Jun


Conflicts
One of the important lesson that I learnt from project management is "Conflict". It is not an easy task to manage a project.. Every one have its own priorities, thoughts and approaches. But it is also critical that all conflicts or disagreements or thoughts be highlighted during the discussion, which is good, if we look at it postively. Some good ideas or potential problems may be identified. Thus, a project manager needs to have the necessary soft skills and "stamina" to manage the stakeholders. Bottomline, it is a tough but challenging job. And it pay well too.  :)

Steven 
16thJun


"Fruits" For Thoughts
We meet after work to discuss on the costing assignment. I thought that
it is not that difficult and we should be able to complete fast. In the
end, we spent 3hrs with a lots of discussion and arguments. Tough to be
involved in a project as a team but we need to manage the conflicts.

Sok Ying
16thJun


TeamWork
The most important key factor is communicate and teamwork.
During discussion of the project there’s bounce to have conflicts. There’s a need to ensure that we understood what we need to input into the project, clarified and get the best solution out of the brainstorm

Christine
16thJun


Thought of Learning
From beginning for starting this assignment, i feel like so lost about what need to input to the project. After discussing with team member and refer to the text book.Then we work toward the idea, seeking advice from Janet, then modify again, submit again..... This really spent a lot of time and energy to fine tune and keep our project on the right track.

From my thought, i think is quite complex and time consuming to handle a project from the stage initiation, planning,implementation, control and terminate cycle. (It just same as what we do now!!) The project manager and the team member will spent a lot of time in every cycle. Every stage require different action. So, i think that the project manager is the most critical person in the project. If the project manager make the wrong decision, it may caused the project failure.

Chew Peng
17Jun

Learning
We use the microsoft project to do the WBS activities and I find that  this tool is very useful for tracking projects timeline. I am glad that I get to learn a new tool which may be useful to my work next time.

Sok Ying
27th June


Project management? Future Career?
Working on the classroom assignment can only give us an superficial insight of what are the tasks and responsibilities of a project manager. It should be more complex, mind clogging and intriguing in the actual scenario. How do we proceed from here if we want to become one?

Steven
28Jun


Risk
Managing risk is part of project management. But it is also part of our daily life too.

Steven
11Jul


"LIFE" Project Management
We are actually practising "Project Management" in our "LIFE", working towards our dreams and goals. clearing one obstacles after another. We are actually PROJECT MANAGER ourselves.

Steven
19Jul


Project Closure
We have finally come to the end - "Project Closure". Tough and not easy. But the most important thing is we enjoy the learning process and ultimately the knowledge that we have gained.

Steven
22Aug

Tutorial Page


Tutorial 1

Implementation of Oracle ERP Supply Chain Planning and Procurement

Background

Company Hurd is a manufacturing company with annual sales of $100M. Over 20 years of marketing effort, the market share has increased tremendously to 20%.

Due to the expanding and dynamic market changes and business needs, management calls for a detailed study to further improve the market share. Hurd targets to increase market share by 10% 2 years after implementation.

Management intends to implement Enterprise Resource Planning (“ERP”) system Oracle to replace the current stand-alone legacy systems used by each individual functions or departments.

This Investment will provide advanced capabilities for communicating, planning, and optimizing supply and demand for all trading parties across all tiers of a supply chain.

For this project, company Hurd will implement Phase I for Planning and Procurement to be completed within 1 year time frame.

Project Organization Chart
















Benefits of Oracle ERP

Supply Chain Exchange provides advanced capabilities for communicating, planning, and optimizing supply and demand for all trading parties across all tiers of a supply chain. Oracle Supply Chain Exchange provides the following benefits:

Reduced inventory levels

Normally, the inventory level is managed based on historical trends and this may have cost and revenue exposure due to over or under supply of inventory respectively. With ERP, it provides the collaborative tools to reduce inventory and free working capital. With clear communication and visibility extends to all trading partners, it allows companies to plan accordingly and is able to have a more predictable inventory level.

Improved visibility across entire supply chains

ERP provides collaborative capability to all trading partners across extended supply chains ensuring access to accurate and timely information. This visibility and easy access to information at any place or at any time, allows companies to work smarter and faster. It facilitates close collaboration between suppliers and supplier’s suppliers, customers and customer’s customers, at the most remote tiers of extended supply chains, transforming fragmented supply chains into responsive supply networks.

Increased velocity of information and material

The speed of the information and material moves between trading partners makes collaboration between companies at all tiers of a supply chain faster, easier and more reliable. Thus, the abilities to communicate in real-time increase the velocity of information and material across supply chain. This results in bottom line savings and increased customer satisfaction.

Improved ability to more accurately promise delivery

Being able to deliver as per promised to meet the customer demand is essential. ERP allows companies to see beyond their tier 1 suppliers to tier x suppliers. This level of visibility allows companies to identify problems, sooner rather than later, and to respond quickly ensuring that a promise made is a promise kept.

The current legacy systems lack the following functions and capabilities:

Collaborative Planning and Optimization

Oracle Supply Chain Exchange provides a common repository for cross-enterprise planning information (for example, demand, supply, and rules governing material flow between Exchange members). It provides message translation capabilities so that information can be uploaded to and downloaded from Oracle Supply Chain Exchange in a variety of formats.

Reduce Cycle Time with Holistic Planning

Optimization, planning, and scheduling of the entire supply chain is part of a holistic planning process. Oracle ASCP combines many elements of planning that have historically forced companies into multi-step planning processes resulting in longer planning cycles and multiple plans to reconcile. Oracle ASCP is able to generate holistic supply chain plans that simultaneously provide long range aggregate planning and short term detail scheduling.

It allows planning of material requirements, capacity requirements and replenishments for all facilities where inventories are stored or products are manufactured. Trading partner’s inventory locations and plants can also be included. Oracle ASCP allows the generation of the equivalent of Distribution Plans, multi-plant Master Schedules (Production Plans) and Material Requirements Plans (Manufacturing Plans).

Optimization for Planners

Oracle ASCP incorporates advanced optimization techniques. Using a simple and intuitive graphical user interface, planners can leverage advanced constraint-based solving technology to ensure that the plan is feasible and respects the constraints, including finite material and resource capacity, and project pegging. Thus, it is able to execute the plan and meet customer’s commitments. Rules can be defined to prioritize demands based on combinations of criteria such as dates, customer priorities, and item priorities. Objectives such as improving profitability or on time delivery performance can be achieved using Oracle ASCP.

Backward Compatibility and Multi-Instance Planning

Using Oracle ASCP, data can be planned from multiple instances and different versions of Oracle Applications. Collection programs let you automatically collect data from Oracle Applications instances on a net change basis. Current Oracle customers can implement Oracle ASCP without upgrading their other Oracle Applications. Interface tables also allow you to collect data from any legacy applications.

Plan the Supply Chain in a Centralized or Distributed Environment

Oracle Advanced Supply Chain Planning (ASCP) allows you to quickly and easily bring all functions within the enterprise into the planning process and enable critical information to flow throughout the global supply chain at Internet speed.

Common Data Model

Oracle ASCP and Oracle’s E-Business Suite share a common data model for planning and execution. And because aggregate planning and detailed scheduling are the same process, there is only one data model. One source of truth means a faster, simpler implementation, higher data integrity, and lower initial and long-term cost of ownership.

Advanced Simulation

Oracle ASCP provides online interactive simulation planning to rapidly simulate and respond to changing conditions. For example, an unconstrained plan and a constrained plan can be generated. Then compare the results based on the performance indicators. You can simulate the effects of changing sources, lead times, safety stocks, order modifiers, shipment methods, in-transit lead times, alternate components, alternate resources, and other planning data.

Increase Planners’ Efficiency with Instant Access to Global Supply Chain Information

Planners need to respond rapidly to a dynamic and complex environment. They need to have instant access to vast amounts of information including supply and demand information about the entire global supply chain. The Planner Workbench streamlines the common activities of planners, while providing easy access to the information needed to answer the tough questions faced by planners. Planners use intuitive customizable tree structures to display detailed information about a plan and get quick and easy access to frequently used information. The trees are organized based on the way work is assigned to planners. This makes access to information simple and intuitive. Distribution planners access information differently than manufacturing schedulers, who ask different questions than buyer-planners

Communicate Across the Extended Supply Chain with Internet-Based Collaborative Planning

Oracle ASCP extends the collaborative features of Oracle Applications. It is built on Oracle’s robust Internet architecture that allows all Oracle Applications to be deployed over the Internet or your corporate Intranet. It is also completely integrated with the other collaborative components of the Oracle E-Business Suite such as Oracle Internet Supplier Portal and Oracle Supply Chain Exchange. Oracle ASCP provides powerful Internet-based collaboration methods and allows you to communicate seamlessly with trading partners.

Oracle ASCP provides low cost web deployment of the entire advanced planning solution. Its architecture is compliant with open Internet standards and the data model is accessible through Java Business Objects and XML. This enables you to extend collaboration with Oracle’s web based adhoc query tools and OLAP tools, or any SQL-based query tool. Oracle’s Internet computing architecture provides an advanced framework for managing today’s collaborative supply chain.

Manage Your Global Supply Chain

Oracle Advanced Supply Chain Planning provides the tools to model and plan your entire supply chain. You can define all of your organizations or facilities including suppliers and customers. The relationships between organizations and the flow of materials can be defined through the supply chain using Sourcing Rules and Bills of Distribution.

Simultaneously Plan Material and Capacity

Oracle ASCP plans material and capacity requirements simultaneously. Run plans that are unconstrained by material and capacity (infinite planning) to determine resource and material capacity required to meet demand due dates. Alternatively, run plans constrained by material and resource capacity (finite planning) to schedule demand within material and resource constraints. Both material and resource constraint violations can be viewed in a single window and easily drill down to see details such as gross requirements, available supply (or capacity), and net requirements for the related materials or resources.

Plan across Manufacturing Modes in a Single Integrated Plan

Oracle ASCP supports full mixed mode manufacturing. It plan make to stock, make to order, assemble to order, and configure to order products simultaneously. Oracle ASCP is fully integrated with all Oracle Application manufacturing applications, including Oracle Discrete Manufacturing, Oracle Process Manufacturing, Oracle Shop Floor Management, Oracle Flow Manufacturing, and Oracle Project Manufacturing.

Oracle E-Business Suite—the Complete Solution

Oracle E-Business Suite enables companies to efficiently manage customer processes, manufacture products, ship orders, collect payments, and more—all from applications that are built on unified information architecture. This information architecture provides a single definition of the customers, suppliers, employees, products—all aspects of the business. Oracle E-Business Suite enables the sharing of unified information across the enterprise for better decision making with better information.

Push factors for implementation of Planning and Procurement

With the ERP implementation for planning and procurement, there will be an improvement in customer’s satisfaction due to better on time delivery. There is better inventory control due to accurate inventory tracking. Overall there is an integrated system for efficient planning which will benefit the company performance and delivery.















Stakeholder Analysis

Stakeholder analysis refers to the action of analyzing the attitudes of stakeholders towards something (most frequently a project). It is used during the preparation phase of a project to assess the attitudes of the stakeholders regarding the potential changes.

Who are they?

PM – Project Manager
Proc – Planning and Procurement
Mgmt – Management Team (Sponsor)
Fin – Finance
IT – Information Technology
Prod - Production


Stakeholder Analysis Techniques: Mapping I: Position / Importance

Under the Problematic:

We target the stakeholder – Production is grouped under the Least Importance with the highest Oppose because they are at the lowest hierarchy, their mindset is still resistance to the change in adapting to the new system implementation.


Under the Antagonistic:

We target the stakeholder – Planning & Procurement is grouped under the Most Antagonistic with the highest oppose because they will higher bargaining power because they have more problem to face and data to console during the implementation so they are resistance to the change in adapting to the new system implementation.


Under the Supporter:

We target the stakeholder –Finance, Mgmt and PM as they will support the implementation of the Oracle as more revenue and greater benefit will be generated after the implementation. IT also supports as they are the first to start-up with the project and involve in the changes and training in the System.

Stakeholder Analysis Techniques: Mapping II: Power / Predictability
Under the Unpredictable but manageable Response:

We target the stakeholder – Production is grouped under the least Power and low predictability because they will just follow accordingly to the schedule changes from higher level

Under the Powerful but Predictable:

We target the stakeholder – IT, management and Finance is grouped under the highest Power and high predictability because they will experience the most impact if there is any issue during the implementation and they have the final say in the decision making.


Under the Greatest Danger or Opportunity:

We target the stakeholder – Planning and Procurement is grouped under the High Power and low predictability because they are in a position to block or support new programs. This stakeholder may test out the project process with other stakeholders prior to detailed execution.

Stakeholder Analysis Techniques: Mapping II: Power / Interest

Under Minimal Effort:

We target the stakeholder – Production is grouped under the Low Power and lack of interest because they are just follow instruction from the Management

Under the Keep Informed:

We target the stakeholder –Planning & Procurement is grouped under low Power and high level of interest because they more interested in the progress of the implementation

Under the Key Player:

We target the stakeholder – IT, Finance and Management is grouped under the high Power and high level of interest because they need to ensure the successful implementation of the project and to resolve any issue faced during the implementation

For Key Player, these stakeholders should be given primary consideration before any decision is made.

Project constraints: Performance, time and resources Trade offs

During the implementation, the project manager needs to consider the scope and cost trade off when an unexpected problem occurs.

The performance of the project must be reliable and accurate as it will affect the overall organization performance. This cannot be compromised while adjustment may still be able to be made on the budget and time of the project. It is still acceptable if the cost does not exceed 20% of the budget and is behind schedule by 6 months.


 













Critical Success Factors

Ownership, commitment and involvement from the top management are important. A clear direction is embraced at all levels and top management to support the project team with the necessary resources until the project is completed.

The right selection of software is the key to successful implementation. If the software is chosen wrongly, it will be difficult for the software vendor to implement correctly accordingly to your business processes.

Organization should follow accordingly to defined implementation process steps given by the experts. During implementation, organizations might come to know about some functionality and would want to add those functionalities at the same time. There is a need to discuss with the experts for any process changes. If not, this may have an impact on the project cost and schedule.

An effective change management strategy and plan is required to cater for the transition from the legacy to the new Oracle world. This is important as the workflow and responsibilities will be different.

Organization should check the track record of vendor implementation partner. They may ask the vendor for client visit to see the running software and its functionalities

There should be awareness, capability and motivation at all levels among all stakeholders.

There is necessary infrastructure available for the effective implementation of the system.

Responsibilty Matrix
















Legend:
R – Responsible
A – Accountable
C – Consulted
I – Informed
PM – Project Management
Log – Logistics
Proc – Procurement and Planning
WH – Warehouse
Mgmt – Management
Fin – Finance
IT – Information Technology
Prod - Production


Tutorial 2


Mind Mapping Exercise
















The mind mapping diagram shows an overview of the processes for the ERP implementation.
The team has identified 8 main stakeholders, mainly the Management, Vendor, Sales and Marketing, Finance, IT, Production, Planning and Procurement, Logistics for the implementation. Phase 1 implementation will be on Planning and Procurement.

Tutorial 3

Work Breakdown Structure
















Tutorial 4

Project Costing

Initial Project Costing Breakdown



















Implementation of ERP Planning and Procurement activities on nodes -Network Diagram and Critical Path Analysis

















The critical path is from 1, 2, 4, 5, 6, 8, 9,10,12,13,14,15,15,16,17,18,19


Start and Finish Network Computation


CPA Activities - Initial Plan















Initial Schedule – Gantt Chart
















Tutorial 5

SWOT Analysis for the implementation of Oracle Planning and Procurement

SWOT analysis is a strategic planning used to evaluate the strengths, weakness, opportunities and threats which involved a project. Company Hurd uses SWOT analysis for evaluation after the implementation of the ERP for planning and procurement.

















***From SWOT Analysis, we derived that most of risk are cause by internal factors which fall under the weakness portion.

STRENGTH:

Alignment with business strategy - by implementation of Oracle allows company to generate more revenue, profits and operation efficiency.

System Infrastructure – readiness of system Infrastructure such as network connection, IT team, Hardware and software support in the implementation of Oracle
Stable market share – with strong financial figure will attract more investors. We can have more budgets in the implementation of Oracle.

WEAKNESS:

Data integrity – data interface issue due to complexity of input data. Transmission of the data from spreadsheet into system or download from system might cause discrepancy in the data retrieve.

Data Accuracy - data input by the end users for the data migration must be accurate as it will affect the end result.

Short learning curve for employees to adopt to oracle - due to tight training schedule, employee will have difficulty in master the system. With the new implementation of Oracle, a lot of work flow process is being changed from manual to systemization.

Server Breakdown, Interface Problem – due to increase in the flow of data which lead to traffic data overflow, if system is unable to support will cause server breakdown. Interface problem can be caused by the user if they have input the wrong sequences which validate the system.

Resignation of key project staff – will mess up the schedule if the handover job are not done properly.

Resistance to change - employees may not want to adopt and learn new changes. Longer time and resources may be taken to train the staffs.

Lack of knowledge expertise in oracle – everyone are new to oracle need more time to explore. IT personnel might be new to process system and interface sequence.


OPPORTUNITIES:

Improve Competitive advantage – utilize the resources and deliver the same benefit as the competitive but at a lower cost. This would create competitive advantages so as to create value to our customers and generate more profit.

New Business opportunities – by capture new market opportunities so as to increase the market share. The company is able to respond fast to customer’s dynamic needs after the Oracle implementation.

THREATS:

System security threats – data privacy, authentication or even subject to virus attack.

Change of business environment - pose a threat to financial figure which will affect the company’s ability to sponsor the project due to tight financial constraint.

Risk Analysis for the implementation of Oracle Planning and Procurement

After the SWOT analysis and assessment, we have identified the top 5 risk events. The risk are Prepare design & prototype, Planning & procurement data collection, Verify planning end result & schedule, review hardware & software and Project go live which is shown in the risk response matrix

Risk Response Matrix















It is further identified to 2 top risk events which is Planning & procurement data collection and Verify planning end result & schedule.

Impact and Probability Matrix


Project Costing – Initial versus Delay Cost Summary

















CPA Activities - Delay in Schedule Plan


Delay Schedule –Gantt Chart


With the assumption that there will be a 48 days delay each in Planning & procurement data collection and Verify planning end result & schedule events, we have reviewed the Critical Path Analysis. The overall project schedule is delayed by 96 days with the critical path remains unchanged. The overall schedule has been delayed from 196 to 292 days per the Earliest Finished Date.

The critical path is from 1, 2, 4, 5, 6, 8, 9,10,12,13,14,15,15,16,17,18,19

Due to the delay, the investment cost has increased by 1.45% from $569k to $577K which is mainly due to the additional direct labour and contingency cost. As such, ROI has reduced from 12.4% to 10.8% and the breakeven duration has increased from 1 to 1.16 years.


Conclusion

With the Oracle Supply Chain Planning and Procurement implementation, the company can work efficiently through the development and implementation to quickly achieve business results.

Tutorial 6

Implementation of ERP Oracle Supply Chain Planning and Procurement

Project Handover
Project Management: Finalization phase
Project Handover Report -> Project Completion Report

Action Statement


Prepared by : Eng Chew Peng
Title : Project Manager
Location : Yishun Building 1
Version No : 1.0
Version Date : 1 Aug 2010
Status : Draft/Final review/Sign off
DMS ref no. : NA
File/Doc no. : NA

Document control sheet
Contact for enquiries and proposed changes

If you have any questions regarding this document or if you have a suggestion for Improvements, please contact:
Project Manager : Eng Chew Peng
Phone : +65 98889999
Version history
Project Handover approval
The following officers have approved this document.
Sponsor
Name : Mr Hurd on behalf of Management Team
Position : Managing Director
Signature :                             Date :
The following officer endorsed this document.
Name : Eng Chew Peng
Position : Project Manager
Signature :                            Date :

Project Team Member:

Liew Sok Ying

Steven Khoo

Christine Teo


Project Performance

The project has been implemented successfully with no major system performance issues.
Overall, the activities have been delayed by 96 days due to a delay in 2 of critical activities. Thus, this has affected the project completion and has also used up the contingency cost factored in for this project. After taking into consideration of the contingency cost, the project has exceeded by $8.25K.


Operational Handover

Overview of Impacts

The gain from this investment outweighs the investment cost due to an increase in the productivity and operation efficiency. As such, this results in a reduction in the labour and inventory costs.

Risk

Data accuracy and integrity continues to be an on-going issue which requires the efforts of all departments to ensure proper data updating and transmission.

Handover

The first major phase in delivering a successful ERP implementation is to define the actual goals of the project. This involves identifying and documenting the features and functionality delivered during the implementation phase of the project.

As the project proceeds, there is a need to review the documented requirements lists to check that the current progress in the direction of the project. Without the documented requirements, it will be difficult to manage as new and unexpected changes creep into the project’s implementation.

There should be a constant follow up on the long term maintenance support.



Activities Page

Location: SP, Dover
Time: 1200 to 1700
Date: 09th May 2010

Agenda.
1. List down the project objectives.
2. Scoping of the project which includes:
  • Estimated duration
  • Estimated cost
  • Responsibility matrix
  • Current issues
  • Man power requirements
  • Resources requirement
Minutes of meeting.
Time            Activities 
1200-1230   Generally discuss the ERP implementation process.
1230-1330   Define the objective, project schedule constraint and estimate project cost constraint.
1330-1415   Define the resources equipment and man power requirement.
1415-1530   Discuss and identify the current legacy system and shortcoming of the system.
1530-1700   Discuss and identify benefits of Oracle Supply Chain Exchange.



Location: Singapore Poly, Dover
Time: 1230 to 1700
Date: 16 May 2010

Agenda.
Work on Process Mind Mapping

Minutes of meeting.
Time                  Activities
1230 to 1415    Process Mind mapping. Discuss and identify the key area for ERP implementation. (ideas Deliverable for WBS)
1400 to 1600    Process Mind mapping. Discuss and identify the key function of each key area.(Ideas sub-deliverable for WBS)
1600 to 1700    Using the mind mapping software to draw the mind mapping process.



Location: Singapore Poly, Dover
Time: 1030 to 1700
Date: 23 May 2010

Agenda.
1. Must read up the following links b4 attending this meeting.
Critical cos need to review whether we are adopting the right approach.
http://www.slideshare.net/ciprian/project-initiation-and-scoping
http://www.lindsay-sherwin.co.uk/project_framework/htm_project_management/4c2_projectscoping.htm
2. Redo Responsibility matrix
3. Review Mind Mapping
4. Work on WBS (Work Breakdown Structure)



Minutes of meeting.
Time                 Activities
1130 to 1400   Browse thru the website and read the guide line for project initiation.
http://www.slideshare.net/ciprian/project-initiation-and-scoping
http://www.lindsay-sherwin.co.uk/project_framework/htm_project_management/4c2_projectscoping.htm
                        Discuss the new idea and idea of improvement for tutorial one base on website above
                        Decide to implement the element planning and procurement due to time constraints.
1400 to 1500    Discuss and draw the WBS based on the mind map.
1500 to 1600    Discuss and modify the responsibility matrix.


Location: SP, Dover
Time: 1000 to 1900
Date: 30th May 2010

Agenda.
1. Review through the Janet's list as shown below.
2. Please see attached. Will need to go through this process again.
3. Review Mind Mapping and WBS again. Need to submit WBS tutorial 3 and activity 4 next week.


Minutes of meeting.
Time                 Activities
1000 to 1200   Review through the Janet's list as shown in email.
1200 to 1300   Review WBS is link to responsibility matrix. Amend responsibility matrix.
1300 to 1500   Add on the background, situation problem and trade off anaysis. Amend SMART objective, Project Title.
1500 to 1730   Add on the SWOT Analysis, Stakeholder Analysis.
1730 to 1800   Add on Project Organization Chart
1800 to 1900   Review that we fulfill the requirement from Janet.


Location: SP, Dover
Time: 1100 to 1700
Date: 13th Jun 2010

Agenda.
1) Make changes per discussion with Janet.
2) Work on WBS on the detailed task, need to make use of the format shown in the lesson note.

Minutes of meeting.
Time                Activities
1100 to 1200   Review and discuss the current WBS & Responsibility Matrix.
1200 to 1300   Modify the WBS and Responsibility Matrix.
1300 to 1500   Create Brain Storm on the Action Plan to build up the scope of work.


Location: SP, Dover
Time: 1830 to 2140
Date: 15th Jun 2010

Agenda
To work on Tutorial 3 ie Project Costing

Minutes of Meeting
Time                  Activities
1830 to 2140    Work on Project Costing. Completed and submitted to Janet.

Location: SP, Dover
Time: 1100 to 1730
Date: 27th Jun 2010

Agenda
To work on Tutorial 4 using microsoft project to create schedule. Do AON and identify critical path.
Make changes to WBS as per Janet's recommendation

Minutes of Meeting
Time               Activities
1100 to 1300 Makes to the WBS as per Janet's recommedation
1300 to 1400 Review and discuss on the start and end date for the WBS activites.
1400 to 1500 Input the activites, start and end date into microsoft projects.
1500 to 1730 Draw AON and identfy the critical path

Location: SP, Dover
Time: 1100 to 1900
Date: 11.07.2010

Agenda
Add in the closure part - element "Go-Live"
Change accordingly for the linkage process, change WBS, Responsibility Matrix, Costing, and Schedule.
Starting tutorial 5

Minute of Meeting
Time               Activities
1100 to 1200 Modify and add in the project closure - "Project Go-Live"
1200 to 1400 Modify WBS, Responsibility Matrix, Costing, Schedule by add in the project closure.
1400 to 1600 Identify the risk and risk analysis
1600 to 1900 Risk Response Matrix


Location: SP, Dover

Time: 1100 to 1900
Date: 18.07.2010

Agenda
To work on Tutorial 5 Risk Management, review costing.

Minute of Meeting
Time               Activities
1100 to 1330 Review Costing
1330 to 1900 Tutorial 5 - Risk Management




Location: SP, Dover
Time: 1100 to 1700
Date: 01.08.2010


Agenda

Make changes to WBS, Risk analysis. CPA.
Started on Tutorial #6 Closure

Minute of Meeting
Time                 Activities
1100 to 1300    Tutorial #6
1300 to 1600     Risk Analysis , WBS
1600 to 1700     CPA

Location: SP, Dover

Time: 1100 to 1700
Date: 14.08.2010

Agenda
Review and amend on document report

Minute of Meeting
Time               Activities
1100 to 1700 Review, amend document report. Work for power point as well at the same time.

Location: SP, Dover
Time: 1100 to 1800
Date: 21.08.2010

Agenda
Review Janet Comment on tutorial 4 to 6
Work on power point presentation and final word report

Minute of Meeting
Time               Activities
1100 to 1330 Review Janet comment and make amendment accordingly.
1330 to 1530 Up dated E port-folio
1530 to 1800 Review, amend document report. Work for power point as well at the same time.


Location: SP, Dover
Time: 1100 to 2100
Date: 22.08.2010

Agenda
Update blog, project report and presentation slides.

Minute of Meeting
Time               Activities
1100 to 1330 Work on project report
1330 to 1530 Updated E portfolio
1530 to 2100 Work on presentation slides